Last week, the German multinational acquired another cement factory in occupied Western Sahara.

Published 09 May 20

Photo above: HeidelbergCement already controlled one cement factory in Western Sahara, the CIMAR unit outside of El Aaiun, seen in the picture. Now, they own a second factory nearby. 

The Moroccan cement company Cimenteries Marocaines du Sud (CIMSUD), operating a cement production unit near El Aaiún in occupied Western Sahara, has now been taken over by the German company HeidelbergCement. 

This is clear from a press release issued on 4 May 2020 by Ciments du Maroc [or download]. The press release explains that the acquisition was finalised on 4 May 2020, following an agreement signed with the previous owner Anouar Invest on 26 July 2019.

The buyer, Ciments du Maroc, is 51% controlled by the German multinational cement group HeidelbergCement.

The cement industry is fundamentally important for the Moroccan occupation of the territory, including settlement policy and key industries that are being developed in violation of international law. 

Moroccan media wrote in 2016 that the Anouar group's decision to construct the CIMSUD factory was "in order to support the development of the southern regions in the wake of the many infrastructure investment projects (OCP complex, port, technopole, roads, etc.) and housing projects planned in the southern provinces. The new unit will thus make it possible to meet the growing demand for cement in the region". [or download]

The research division of the German Bundestag just last year published a report on the legal consequences of Morocco's settlement policy in Western Sahara, a territory it has illegally occupied since 1975. Through its production of cement, HeidelbergCement is a key partner of Morocco's illegal annexation and settlement practices as described in the report of the Bundestag division.

From what Western Sahara Resource Watch (WSRW) understands based on media reports, the construction of the CIMSUD factory has met with several delays. CIMSUD "is experiencing delays in construction", Jeune Afrique reported on 30 July 2019 [or download]. "Commissioning was scheduled for July 2017, according to the group's communication. According to our information, it should not be delayed any longer", Jeune Afrique described. 

As late as 4 May 2020, the same day as the completion of the HeidelbergCement takeover, Moroccan media reports were not clear as to whether the factory is finished or not. Challenge.ma told that the previous owner Anouar Invest had still not completed the two large investments it had set out some years before - one of which was the CIMSUD. 

The CIMSUD factory is thus the second unit that the German group controls on occupied land. Through Ciments du Maroc, HeidelbergCement already owned the CIMAR cement unit on the outskirts of El Aaiun city. 

WSRW has on several occasions contacted HeidelbergCement regarding the CIMAR operation, but has never received an answer. The issue of HeidelbergCement's operations on occupied land was addressed at the company’s AGM in 2019 by a Saharawi refugee in the name of the sahrawi youth and of the German NGO 'Kritische Aktionärinnen und Aktionäre'. Instead of answering the question, the company explained that it supports local sports clubs. 

The company consistently presents Western Sahara as part of Morocco, in contrast to the United Nations and international courts. 

The CIMSUD factory itself was constructed by another German company, ThyssenKrupp, according to a press release of 17 February 2016 [or download]. Here is another undated release from Anouar's initial construction of the factory [or download].


 

Morocco spends most of EU's fish support in occupied land

Most of the EU's financial support to Morocco under the EU-Morocco fisheries agreement has been spent on occupied land, new government report reveals. 

25 February 21

Siemens Energy only relates to Morocco in Western Sahara

Siemens Energy will only talk with the government of Morocco with regard to Western Sahara, according to recent company statement.

18 February 21

Continental has left occupied Western Sahara

The German company Continental has not renewed its supply contract with the Moroccan national phosphate company that exploits the controversial Western Sahara phosphate mine.

11 February 21

China Molybdenum silent on potential conflict mineral imports

WSRW has tracked shipments of phosphate rock from occupied Western Sahara all the way to an industrial compound in Cubatão, Brazil.

09 February 21